|

April 11, 2009
Section 2 complete -
Section 3 under construction
C.W.
Matthews contractor progressing into Section 3 from Killian
Hill Road to Highpoint Road
C.
W. Matthews has completed installation of most of the concrete medians
in Section 2 from Stone Drive to Killian Hill Road with the
exception of the final stretch in front of the Publix Shopping
Center and beginning
January 2009 moved into Section 3 from Killian Hill Road to
Highpoint Road. The transition and merge just before Killian
Hill is not the final design as the contractor will install
three permanent travel lanes and turn lanes at this intersection
upon final completion.
The
Jessica Daron / Paxton Lane extension is also now paved - removing
six curb cuts from direct access to U.S. 78 and placing them on a
parallel street improving safety and mobility. This is the same area
the Evermore CID recently completed the installation of 2,100 feet
of 8" sewer line that supported the announcement of the Evermore
Urgent Care $60 million private medical development. Patrons may now
travel between the Yellow River Game Ranch and Killian Hill Road
without ever accessing U.S. 78 - providing additional connectivity
for businesses in the area.
You most likely
have also noticed the newly installed lighting crossing the
vehicular bridge at the Yellow River. Illuminated in blue during the
evening, the lighting draws added attention from motorists crossing
the bridge improving both aesthetics and safety.
July 7, 2008
Section 1 complete -
Section 2 under construction
C.W.
Matthews contractor progressing into Section 2 from Stone
Drive to Killian Hill Rd.
C.
W. Matthews has completed installation of the concrete medians
in Section 1 from East Park Place to Stone Drive and beginning
July 7, 2008 is moving into Section 2 from Stone Drive to
Killian Hill Road.
The same traffic
control lane sequence will prevail in Section 2 -- three westbound
lanes to Atlanta and two eastbound lanes to Snellville during
construction. At the conclusion of the project, GDOT will provide
three permanent travel lanes in each direction.
The reversible lane
and light system is no longer operating from Killian Hill Road to
East Park Place. Half the 7-mile corridor is now without the
confusing light system.
Remaining
installations in Section 1 include decorative mast arms, signals,
illuminated street signs, and landscaping. Governor Perdue has
issued an Executive Order preventing any planting on state projects
during the drought; therefore, the timing for the installation of
landscape materials is not yet determined.
June 18, 2008
Center medians
installed
C. W.
Matthews contractors moving rapidly through Section 1
C.
W. Matthews began pouring the center median on U.S. 78 this
week. Construction is progressing rapidly through Section 1 that
begins at East Park Place Blvd and continues to Stone Drive. In
addition to the center median, new curbing, sidewalks, and
preparations for landscaping have also been completed.
Subcontractors BB&H and PDP have installed advanced technology
providing motorists with many opportunities to stay informed of
the progress and current conditions. Visit
www.78smh.com for real-time
traffic information and tune to
AM 1620
as you approach the construction zone for lane closures and/or
incident information.
March 12, 2008
Evening Lane Closures
Eastbound right lane closed nightly from 7
p.m. until 5 a.m. from East Park Place to Stone Drive
Lane closures
continue evenings after 7 p.m. between East Park Place and Stone
Drive eastbound. Based on the first few weeks of construction,
congestion and delays are heaviest between 7 p.m. and 8:30 p.m.
beginning at the DeKalb County line and continuing to
Camp Circle headed eastbound. The typical evening rush hours
from 4 p.m. until 6 p.m. appear to be operating without
significant delays.
Delays are made
worse when motorists block the intersections preventing cross street
traffic from clearing during a signal change. After several attempts
to direct traffic in an effort to maintain clear intersections and
numerous warning tickets, Gwinnett County Police Officers have
resorted to citing motorists that block the intersections along U.S.
78 in the construction zone. Please keep all intersections clear.
February 27, 2008
Median
Construction Update
Provided to Evermore CID Board - prepared by
Brett Harrell, CID Executive Director
Roadway
construction began Sunday evening, February 17, 2008 with the
removal of the reversible lights within Section 1 from East Park
Place to Stone Drive. Travel lanes were re-stripped on U.S. 78
providing three westbound lanes toward Atlanta and two eastbound
lanes toward Snellville in Section 1. Construction activities
required in the roadway begin at 7 p.m. and conclude by 5 a.m.
daily.
The phasing plan
performed well during Monday morning rush hour; however, the return
commute during evening rush hour resulted in unacceptable delays –
compounded by a work zone accident. Tuesday the 19th,
GDOT re-timed the signals “on-the-fly” during the evening rush hour
and reduced delays. Timing adjustments will continue throughout
construction to react to changing traffic patterns and to minimize
congestion and delays.
Utility contractors
continue working to relocate facilities outside the construction
zone. All firms are clear of Section 1 with the exception of
removing some non-operable equipment. In Section 2, Walton EMC is
clear, Comcast will be clear by 2/29, AT&T will be clear by 3/30,
AGL will be clear by 3/14, and with the exception of relocation of a
water vault, DWR is clear in Section 2. GDOT has requested all
utilities seed and mulch within Sections 2, 3, and 4 in disturbed
areas. Several potential conflicts remain with walls, mast arms,
sidewalks, etc that continue to receive attention.
Real Time Work Zone
Information Systems are partially operational. The Georgia Navigator website
has featured the U.S. 78 project as well as providing a link to the
initial project website at
http://www.78smh.com .
Landscape and
streetscape issues also remain and those issues are currently under
review.

Coming soon . . . illuminated street signs on U.S. 78
corridor.
February 21, 2008
DOT tweaks
timing on U.S. 78
Will improve evening rush hour commute
Georgia DOT is making adjustments to
the signal timing to improve the evening rush hour transition
from three lanes to two lanes on U.S. 78 within the construction
zone.
Read more >
February 19, 2008
Median work has
begun - traffic shift in place
Nightly
from 7 p.m. until 5 a.m., GDOT contractors are working on U.S. 78,
expect lane closures
From West Park Place to Stone Drive
the roadway has been re-stripped with three westbound lanes (to
Atlanta) and two eastbound lanes (to Snellville). These lanes
will remain throughout construction until such time as the
median is installed.
The right, eastbound lane from West
Park Place to Stone Drive will be closed nightly from 7 p.m. until 5
a.m.
Channel 46 News Video:
http://www.cbs46.com/video/15339385/index.html
February 13, 2008
Roadwork
begins Sunday, Feb. 17 on U.S. 78
Reversible lanes coming down in Section 1
from West Park Place to Stone Drive
The
Georgia DOT
announces roadway work will begin overnight beginning Sunday,
February 17 on the project to remove the reversible lane system
and widen US 78 in Gwinnett County.
Read more >
October 12, 2007
Georgia DOT Clear Zone
Please keep right-of-way clear
Businesses: Please maintain a
clear zone free of any obstructions between the
pink flags / pink paint and U.S.
78. Any remaining signs, light poles, or other obstructions marked
with a blue flag / blue paint
must be removed and may be removed by the contractor at any time
without further notice.
October 3, 2007
Community
questions about U.S. 78 construction activities
The Evermore CID appreciates your continued support
Members of the community surrounding
the Highway 78 construction project have asked several good
questions about the progress.
We have attempted to provide answers and will update the Q&A sheet
periodically as progress continues.
Community Q&A
about the U.S. 78 construction project
September 18, 2007
Georgia DOT Median Safety Project
Information Sheets
Project and corridor fact sheets
The Georgia Department of
Transportation has prepared two brief fact sheets for the
median project and the U.S. 78 corridor.
Project Fact Sheet pdf file
Corridor Information pdf file
Georgia DOT Median Safety Project Update
We've 'cut the cord' to mark the beginning of the project.
Nearly one hundred attended
the ceremonial 'cutting of the cord' to begin the U.S. 78
safety median project on Friday, September 14, 2007. The
importance of this project was demonstrated by those in
attendance: Federal representatives from U.S. Sen.
Chambliss, Sen. Isakson, and Congressman Linder; at the
State level representatives of Lt. Governor Cagle, Sen.
Butler, Sen. Henson, Rep. Everson, and Rep. Cox; from the
County Commissioners Beaudreau and Greene; and
representing several nearby cities Snellville Mayor
Oberholtzer, Lilburn Mayor Bolton, Norcross Mayor Webb,
Snellville Council Member Kautz, and Lawrenceville Council
Member Johnson. The event also attracted numerous
representatives from the Georgia and Gwinnett DOT,
consultants, and two former DOT Commissioners Moreland and
Shackelford.
Most importantly, many local
business owners and citizens attended in support of a
project that will change the future of our community. At
completion, the Evermore community will be safer, less
congested, and more attractive. The Evermore CID thanks
all those that have worked so hard to make this project a
reality.
September 7, 2007
Georgia DOT Median Safety Project Update
Clearing begins September 17, 2007
Contractors will begin
clearing the right-of-way on the south side of U.S. 78
from East Park Place to Stone Drive on September 17. Any
remaining signs, lighting, or other obstructions are
declared abandoned and are subject to removal by the
Georgia Department of Transportation.
All utility companies continue
working throughout the corridor relocating their
facilities. Please keep in mind this is a
CONSTRUCTION ZONE.
Slow down, be alert for utility and/or construction
vehicles and workers to insure safety at all times.
GDOT Press Release: Site work starts Wednesday, 12th and
Groundbreaking Ceremony Friday, 14th
August 8, 2007

June 1, 2007
Georgia DOT Median Safety Project Update
C.W. Matthews
awarded contract at $31.5 million for construction
The Georgia Department of
Transportation has completed final plans for the U.S. 78
safety median project that will remove the reversible lane
and light system and replace it with a landscaped median.
GDOT opened bids for the project on Friday, May 18, 2007
and awarded the contract on Friday, June 1, 2007 to C.W. Matthews Contracting Company the low
bidder with a construction cost of just under $31.5 million. Georgia DOT has authorized Walton Electric and others to
proceed with utility relocation efforts -- that work may
be underway any day.
Including the cost of
right-of-way acquisition, engineering and construction,
the U.S. 78 median safety project is approaching $60
million and is the largest project in the history of the
Traffic Safety and Design division of the Georgia
Department of Transportation. Many of the enhancements and
improvements included in this project would not have been
possible without the tremendous cooperation of GDOT and
the support of Senator Johnny Isakson and Congressman John
Linder. Additional partners improving the final design and
benefit of the project include the Gwinnett DOT, Senator
Saxby Chambliss, Congressman David Scott, and Congressman
Lynn Westmoreland.
Please find below a brief list of details contained in
the final plan documents for the U.S. 78 project:
U.S. 78 Corridor Details
- Urban Principal Arterial roadway
classification
- 2007 Average Daily Trips =
69,060
- Projected 2027 Average Daily
Trips = 95,610
- 24 hour truck traffic = 3%
- 45 mph design speed
- 17% of project within corporate
limits of Snellville
Construction Details
- Project length 6.65 miles all
within Gwinnett County and the 7th Congressional District
- Construction staging in four (4)
phases:
- East Park Place to Stone Drive
- Stone Drive to Killian Hill Road
- Killian Hill Road to Highpoint Road
- Highpoint Road to S.R. 124
- No more than two phases under
construction at any time.
- 15 signalized intersections with
decorative black, fluted posts and mast arms
- Re-synchronization and timing of
all signals from East Park Place to S.R. 84
- 8 additional median openings
- Reversible lanes maintained
during construction outside the construction zone
- Within construction zone, lanes
are re-stripped to provide 3 westbound lanes and 2 eastbound
lanes with a center turn lane
- Ingress and Egress shall be
maintained to all properties during construction
- Three permanent travel lanes (10
foot width) in each direction at the completion of construction
- Numerous right and left turn
decel lanes throughout the corridor
- Much of the work completed
during evening and off-peak hours
- Construction complete by October
31, 2009.
Communication during construction
- 5 Dynamic Changeable Message
Signs
- 2 Highway Advisory Radio beacons
(you will be able to tune to an AM radio station for
construction updates)
- Email and Website construction
updates
- 500 hours of additional law
enforcement and traffic control
Enhancements
- Technology: 8 Closed
Circuit TV Cameras, 8 Radar Detection Devices, new Fiber Optic
Cable -- all looped back to the newly installed signals to
improve synchronization, flow, and congestion management during
construction and beyond
- Landscaping: 222 various
trees; 11,843 various shrubs; 10,452 various groundcover; 3,764
various annuals; planted medians where width permits
- Signage: 65 internally
illuminated street name signs at all cross streets
- Sidewalks: 5 foot wide,
4" thick sidewalks the length of U.S. 78 on both sides of the
roadway
- Jessica Daron Court
extension: Construction during phase 2 of a parallel roadway
connecting the Yellow River Game Ranch to Jessica Daron Court.
This project removes six curb cuts from direct access to U.S. 78
and provides improved safety, mobility, and access to a number
of businesses as well as residents.
- Streetscapes: Decorative
trash receptacles and benches along the corridor and enhanced
lighting at the Yellow River Bridge crossing.
News articles:
Do medians affect your shopping decision?
Work to begin soon on U.S. 78 project
GDOT to accept bids for U.S. Highway 78 median project
Highway 78 median bids due May 18, 2007
|